Advanced Frequencies

Overview

  • OpCon Frequencies are very powerful

  • The Advanced Tab under Frequency List allows addition to or removal from the selected Job Frequency functions
    • Advanced Tab settings are not saved with the Frequency for reuse
    • These settings are saved with the Job
      • Example: Job Start Offset, Build Status, etc.

Options

  • There are several options in Advanced Frequency settings:
    • Start Scheduling On
      • Allows Job creation in preparation of a large change (such as changing vendors)
      • Directs the allocated Frequency or Frequencies not to start until a specified date
    • End Scheduling On
      • Essentially the exact opposite of Start Scheduling On
    • Include in Schedule On
      • Allows variously selected On-Off Dates for a Job to be Scheduled
    • Excluded from Schedule On
      • Essentially the exact opposite of Include in Schedule On
    • Exclude Month from Schedule
      • Used often on Quarterly Jobs which do not run on the first month of quarter

Enterprise Manager

Details
  • OpCon Frequencies are very powerful
  • The Advanced Tab under Frequency List allows addition to or removal from the selected Job Frequency functions
    • Advanced Tab settings are not saved with the Frequency for reuse
    • These settings are saved with the Job
      • Example: Job Start Offset, Build Status, etc.

  • There are several options in Advanced Frequency settings:

  • Start Scheduling On – Allows Job creation in preparation of a large change (such as changing vendors)

    • Directs the allocated Frequency or Frequencies not to start until a specified date
  • End Scheduling On – Essentially the exact opposite of Start Scheduling On

Include in Schedule On – Allows variously selected On-Off Dates for a Job to be Scheduled

Excluded from Schedule On – Essentially the exact opposite of Include in Schedule On

Exclude Month from Schedule – Used often on Quarterly Jobs which do not run on the first month of quarter